How long will it take to excavate a trench that is 8 feet deep by 4 feet wide by 100 feet long if the hourly production rate is 40 BCY and the operator has an efficiency factor of 75%?

Study for the Commercial Contractor Exam. Access hundreds of practice questions and comprehensive explanations to boost your confidence and ensure you're ready for the test!

To determine how long it will take to excavate the trench, first, calculate the volume of the trench in bank cubic yards (BCY). The formula for calculating the volume of a rectangular prism is length × width × height.

The dimensions of the trench are:

  • Depth: 8 feet

  • Width: 4 feet

  • Length: 100 feet

Converting dimensions from feet to yards (since 1 yard = 3 feet):

  • Depth: 8 feet = 8 / 3 = 2.67 yards

  • Width: 4 feet = 4 / 3 = 1.33 yards

  • Length: 100 feet = 100 / 3 = 33.33 yards

Now, calculating the volume in cubic yards:

Volume = length × width × depth

Volume = 33.33 × 1.33 × 2.67 ≈ 117.78 cubic yards (BCY)

Next, consider the production rate and the efficiency factor. The hourly production rate is 40 BCY, but since the operator has an efficiency factor of 75%, the effective production rate is:

Effective production rate = actual rate × efficiency factor

Effective production rate = 40 BCY